The 12-Step Process to Building a Luxury Custom Home in Miami

From lot purchase to certificate of occupancy: the 12-phase process for building a luxury custom home in Miami, with typical timelines and common pitfalls.

This guide draws on EZ BH's direct experience building luxury homes across Miami's most demanding regulatory environments.

Key Facts

TopicKey Takeaway
Cost RangeVaries significantly by neighborhood, finishes, and lot conditions
Timeline18–36 months from lot purchase to Certificate of Occupancy
PermittingMiami-Dade Building Department; expect 4–6 month review cycles
Key RisksFEMA flood zones, HVHZ wind codes, ARB delays, long-lead materials
Best PracticeHire an experienced local CGC before signing a land purchase contract

The short answer: Building a luxury custom home in Miami takes 18–30 months across 12 distinct phases, from pre-purchase due diligence through move-in. Each phase has specific deliverables, key players, and common failure modes. This guide explains each phase in detail so you can manage your project proactively rather than reactively.

Overview: The 12 Phases

  1. Pre-purchase due diligence (2–4 weeks)
  2. Architect selection and schematic design (8–12 weeks)
  3. Owner's representative and budgetary preconstruction (4–6 weeks)
  4. Design development and engineering (12–16 weeks)
  5. Permitting and ARB review (12–30 weeks)
  6. GC selection and GMP negotiation (6–10 weeks)
  7. Site preparation, demolition, and geotech (4–12 weeks)
  8. Foundation and structural shell (16–26 weeks)
  9. MEP rough-in and dry-in (12–20 weeks)
  10. Interior finishes and cabinetry (18–32 weeks)
  11. Punchlist, commissioning, and certificate of occupancy (4–10 weeks)
  12. Move-in, documentation, and warranty period (12 months)

Note that many phases overlap. For example, design development (Phase 4) typically begins before schematic approval is fully complete, and GC selection (Phase 6) can run concurrently with final permitting (Phase 5). The timeline ranges above reflect when each phase is the primary focus of activity, not rigid sequential slots.


Phase 1: Pre-Purchase Due Diligence

Typical Duration: 2–4 weeks

Key Roles

Real estate attorney, land use attorney, civil engineer or surveyor, architect (feasibility), title company.

Deliverables

  • Title commitment and survey
  • Zoning verification report (setbacks, FAR, height limits, lot coverage)
  • FEMA flood zone determination and preliminary BFE
  • Deed restriction and covenant review
  • HOA/ARB design guidelines review
  • Utility availability confirmation (FPL capacity, water/sewer connection)
  • Preliminary massing feasibility (what can be built within envelope)

What to Do

Before closing on any lot in Miami, commission a full due-diligence review. Zoning in Miami-Dade is complex: the city of Miami uses the Miami 21 form-based code, Miami Beach has its own zoning ordinance, and each municipality has distinct regulations. A single-family RS-1 lot in Coral Gables and an RS-1 lot in Miami proper may have very different effective development envelopes.

Obtain the most current FIRM panel for the parcel from the FEMA Flood Map Service Center (msc.fema.gov) and understand the Base Flood Elevation. If the lot is in a VE or AE zone, an elevation certificate should be part of your due diligence. Have a civil engineer or licensed architect run preliminary numbers on buildable square footage, setbacks, and parking requirements before you finalize your offer price.

Common Gotchas

  • Deed restrictions that prohibit or restrict certain architectural styles
  • Utility easements that eat into buildable area
  • Historic designation or contributing-structure status that limits demolition
  • Flood zone category that requires 3–5 feet of fill, dramatically changing finished floor elevation and approach design
  • Septic-only parcels with no sewer connection available (limits construction program)

Phase 2: Architect Selection and Schematic Design

Typical Duration: 8–12 weeks

Key Roles

Owner, owner's rep (if engaged), architect of record, interior designer (early engagement recommended).

Deliverables

  • Executed AIA B101 Owner/Architect Agreement
  • Architectural program (room list, adjacency matrix, area targets)
  • Site analysis and context study
  • 2–3 schematic massing options
  • Selected schematic design package (floor plans, exterior elevations, roof plan, site plan)
  • Preliminary budget validation against schematic

What to Do

Interview at least three architects. For Miami luxury residential work, look for architects with demonstrated experience in your specific neighborhood and an understanding of Miami-Dade's HVHZ structural requirements. Review completed projects, speak with prior clients, and verify Florida licensure through the Department of Business and Professional Regulation (DBPR) at myfloridalicense.com.

Schematic design should result in a clear spatial concept that you have reviewed, red-lined, and approved in writing before proceeding to design development. Changes are cheap in schematic — they are expensive in construction documents and very expensive during construction. Invest time here.

Engage your interior designer during schematic design, not after. Interior designers who join after construction documents are complete face significant constraints and routinely generate expensive change orders to accommodate their design vision. Early engagement allows interior programming to inform architectural decisions.

Common Gotchas

  • Schematic approval without a realistic budget check — leading to shock in later phases
  • Program creep: the house grows during schematic without corresponding budget adjustment
  • Architect-client scope misalignment on engineering services (structural, MEP, civil — are they in the architect's fee or additional?)
  • Failure to coordinate with interior designer on ceiling heights, beam locations, and wet wall positions

Phase 3: Owner's Representative and Budgetary Preconstruction

Typical Duration: 4–6 weeks (often overlapping Phase 2)

Key Roles

Owner's representative (OPM/PM), cost estimator, owner.

Deliverables

  • Owner's rep contract
  • Preconstruction cost estimate (Class C / order-of-magnitude) against schematic
  • Project delivery method recommendation (design-bid-build, CMAR, design-build)
  • Project master schedule (preliminary)
  • Cash flow forecast
  • Procurement strategy for long-lead items

What to Do

An owner's representative (owners' rep, OPM, project manager) acts as your professional advocate throughout the entire project. Unlike the architect (who has a professional obligation to design excellence) or the GC (who has a commercial interest in their own margin), the owner's rep is fiduciarily aligned with you. They validate budgets, manage the design team, run competitive procurement, and serve as your daily presence on site decisions without the emotional investment that often clouds owner judgment.

For projects above $5M, a competent owner's rep fee of 3–5% of construction cost routinely yields 5–15% in project savings through competitive procurement, change-order discipline, and schedule management. They pay for themselves.

Common Gotchas

  • Hiring an owner's rep after the GC is already selected — losing the procurement leverage
  • Confusing an owner's rep with a project manager employed by the GC (conflicts of interest)
  • Insufficient budget validation at schematic — entering design development with an unrealistic program

Phase 4: Design Development and Engineering

Typical Duration: 12–16 weeks

Key Roles

Architect of record, structural engineer, MEP engineer, civil engineer, geotechnical engineer, landscape architect (early), interior designer, owner's rep.

Deliverables

  • Design development drawings (~50% construction document level) for all disciplines
  • Structural engineering schematic
  • MEP design development (HVAC zoning, plumbing fixture schedule, electrical service sizing)
  • Geotech report (soil borings, foundation recommendations)
  • Updated cost estimate (Class B) against design development
  • Interior design scheme (materials, finishes, fixture selections)
  • Long-lead procurement list (windows, stone, custom millwork)

What to Do

Design development is where the project transitions from concept to buildable reality. Every system must be coordinated: the structural engineer's beam depths affect ceiling heights; the MEP engineer's ductwork routing affects soffit conditions; the interior designer's stone selections affect structural loads if very heavy materials are specified.

Commission the geotechnical investigation during this phase. Geotech data shapes foundation design — without it, the structural engineer must assume conservative (expensive) conditions. Soil borings should be taken at the actual build location.

Begin procurement of the longest-lead items during design development, not after permits issue. Custom windows and doors for a Miami luxury home can take 20–30 weeks to fabricate. Imported stone requires slab selection 12–18 months before installation. Custom millwork shops in Miami are frequently booked 9–12 months ahead. If you wait until permits are in hand to order these items, you will extend your schedule by 4–8 months.

Common Gotchas

  • Coordination conflicts between disciplines discovered late — beam clashes with ductwork, plumbing conflicts with structural columns
  • Interior finish selections not made until mid-construction, generating expensive change orders
  • Geotech surprises requiring foundation redesign after construction documents are 80% complete
  • Pool and landscape not designed until after structural shell, creating coordination problems

Phase 5: Permitting and ARB Review

Typical Duration: 12–30 weeks (most variable phase)

Key Roles

Architect of record, permit expeditor, civil engineer, structural engineer, MEP engineer, owner's rep, land use attorney (if variances needed).

Deliverables

  • 100% construction documents (architectural, structural, MEP, civil)
  • Building permit application and all supporting documentation
  • ARB/Board of Architects approval (where required)
  • SFWMD environmental resource permit (where required)
  • FPL service agreement and load approval
  • Issued building permit

What to Do

Permitting is where Miami projects most frequently derail their schedules. Each municipality has different processes: the City of Miami uses an electronic permit portal (ePlan); Miami Beach has its own system with historic preservation and ARB layers; Coral Gables has the Board of Architects process. Comments from plan reviewers must be responded to in writing, and re-reviews take additional weeks.

Hire a professional permit expeditor for any project over $3M. An experienced expeditor knows the specific reviewers, understands common comment categories, and can often resolve issues with a phone call or in-person meeting that would otherwise generate a formal review cycle taking 3–6 weeks.

For projects in Coral Gables, start the Board of Architects process as early as possible. The BOA meets monthly and provides feedback in rounds — a complex project may require 3–4 BOA hearings, adding 3–4 months to the permitting schedule.

Common Gotchas

  • Incomplete permit submittals triggering immediate rejection and restart of review clock
  • Failing to apply for FPL service upgrade early (8–16 week lead time independent of building permit)
  • SFWMD permit required for dewatering or significant site grading near waterways — often overlooked
  • Revised design post-ARB requiring re-coordination of structural and MEP drawings

Phase 6: GC Selection and GMP Negotiation

Typical Duration: 6–10 weeks

Key Roles

Owner, owner's rep, architect, 3–5 general contractors invited to bid.

Deliverables

  • Invitation to bid (ITB) package
  • GC qualification submissions and reference checks
  • Competitive bids or GMP proposals
  • Leveled bid analysis
  • Negotiated GMP or stipulated-sum contract (AIA A101 or owner-drafted)
  • Construction schedule (CPM, to be updated through construction)
  • Payment application schedule and retainage terms

What to Do

Competitive bidding — inviting 3–5 qualified GCs to price the same set of construction documents — is the single most reliable way to establish fair market pricing and prevent cost inflation. On luxury projects, the difference between the low and high bidder often exceeds 15–25%. An owner's rep who manages this process professionally, levels the bids (ensuring all contractors priced the same scope), and negotiates the GMP can frequently recover their entire fee in this phase alone.

Qualify GCs rigorously. In Miami's luxury residential market, dozens of contractors claim expertise in ultra-high-end construction. Ask for: completed project references in the same price tier, current bonding capacity, subcontractor lists, superintendent experience, and their specific plan for managing Miami's specialty trade market. Visit completed projects with the client.

Common Gotchas

  • Selecting a GC before completing design development — getting a GMP against incomplete drawings provides false security
  • Not leveling bids: a low bid that excluded significant scope items is not a real savings
  • Underestimating the importance of the GC's superintendent — the superintendent runs the daily job, not the principal
  • Inadequate retainage terms — retain 10% through substantial completion, then 5% through final CO

Phase 7: Site Preparation, Demolition, and Geotech

Typical Duration: 4–12 weeks

Key Roles

GC, demolition subcontractor, geotechnical engineer (monitoring), civil engineer, owner's rep.

Deliverables

  • Demolition complete, debris hauled
  • Asbestos/lead abatement complete (pre-1978 structures)
  • Site graded to civil plan
  • Dewatering system installed and operating (if required)
  • Temporary utilities established (power, water)
  • Tree removal permits and tree barricading for protected trees
  • Foundation stakeout survey

What to Do

Pre-demolition asbestos and lead surveys are required for any structure built before 1978 and are environmentally mandated before structural demolition begins. Results determine abatement scope — budget 3–6 weeks for abatement if contaminated materials are found.

Miami-Dade's urban tree ordinance protects trees above certain caliper sizes — violations carry significant fines. Coordinate with the county's DERM (Department of Environment Resources Management) on any significant tree removal or relocation.

Common Gotchas

  • Asbestos abatement scope that is larger than estimated, delaying foundation start
  • Underground utilities not shown on existing drawings, discovered during excavation
  • Dewatering permit from SFWMD not obtained in advance, delaying excavation
  • Protected tree removal without proper permits — costly fines and required mitigation planting

Phase 8: Foundation and Structural Shell

Typical Duration: 16–26 weeks

Key Roles

GC, foundation subcontractor (pile driving or auger-cast), concrete subcontractor, structural engineer (special inspection), threshold inspector, owner's rep.

Deliverables

  • Auger-cast, driven, or spread-footing foundation system complete
  • Foundation inspection passed
  • Concrete block or poured-concrete structural walls complete
  • Poured concrete columns, tie beams, and bond beams complete
  • Structural steel (if any) complete
  • Roof structure complete
  • Dry-in inspection: framing inspection passed

What to Do

Foundation work in Miami is the most geotechnically variable phase of construction. Auger-cast piles are the most common approach for luxury homes in waterfront or high water-table areas. Pile depth and diameter are specified by the structural engineer based on geotech data — in-field conditions may require design changes if subsurface conditions differ from boring results.

Florida's High Velocity Hurricane Zone requires a specific structural system: concrete masonry unit (CMU) walls, poured concrete columns at specified intervals, continuous tie beams at floor and roof lines, and hurricane-rated connections at all structural joints. These requirements are more stringent than most other US jurisdictions and add cost — but they are also what allows Miami homes to withstand Category 4–5 hurricane winds.

Special inspection of concrete placement, pile installation, and reinforcing steel is required under the Florida Building Code for structures meeting threshold criteria. The special inspector is retained by the owner (not the GC) to provide independent quality assurance.

Common Gotchas

  • Pile refusal at unexpected depth — requiring redesign and additional mobilization cost
  • Concrete test failures requiring core sampling and potential remediation
  • Hurricane-anchor installation errors discovered at framing inspection — expensive to retrofit
  • High water table flooding foundation excavation — dewatering system underspecified

Phase 9: MEP Rough-In and Dry-In

Typical Duration: 12–20 weeks

Key Roles

GC, HVAC subcontractor, plumbing subcontractor, electrical subcontractor, low-voltage/automation contractor, roofing subcontractor, owner's rep.

Deliverables

  • Roof system complete (secondary water barrier, primary roofing material)
  • Hurricane-impact windows and doors installed
  • HVAC ductwork and equipment rough-in complete
  • Plumbing rough-in complete (supply, drain, waste, vent)
  • Electrical rough-in complete (conduit, wire, panel rough-in)
  • Low-voltage rough-in complete (data, AV, security, automation)
  • Rough-in inspections passed for all disciplines
  • Insulation complete

What to Do

The dry-in milestone — when the roof and all exterior openings are permanently closed — is the most critical schedule gate in construction. Before dry-in, weather events can flood the interior and damage materials. Achieving dry-in as quickly as possible after the shell is complete minimizes weather risk exposure.

Miami's climate creates specific MEP challenges. HVAC systems must be sized for Miami's extreme humidity and heat load — undersized systems create moisture problems that lead to mold, a significant liability in South Florida. Ducted air handlers in attic spaces must be properly insulated; condensation on insufficiently insulated ductwork in the humid Miami attic is a common source of future moisture problems.

The low-voltage and automation rough-in phase is critical and often undersupervised. The backbone conduit, junction box placement, and wire pulls for a sophisticated home automation, AV, security, and lighting control system require detailed coordination between the low-voltage contractor and the automation designer. Mistakes here are expensive to remedy after walls are closed.

Common Gotchas

  • Coordination conflicts between duct runs and beam locations, discovered after framing is complete
  • Window delivery delays (20–30 week lead times for custom impact glazing) stalling dry-in
  • Undersized HVAC equipment specified before the envelope was fully designed, requiring upgrade after rough-in
  • Missing low-voltage conduit runs discovered after drywall, requiring costly remediation

Phase 10: Interior Finishes and Cabinetry

Typical Duration: 18–32 weeks

Key Roles

GC, drywall subcontractor, plaster/stucco subcontractor, tile subcontractor, flooring subcontractor, custom millwork fabricator/installer, painter, interior designer, owner's rep.

Deliverables

  • Drywall and plaster complete
  • Custom millwork fabricated and installed (kitchen, baths, wardrobe rooms, library)
  • Stone and tile installed (floors, walls, countertops)
  • Hardwood flooring installed and finished
  • Painted and finished walls and ceilings
  • Doors, hardware, and trim complete
  • Plumbing fixtures installed (trim-out)
  • Electrical fixtures installed (trim-out)
  • HVAC trim-out (grilles, thermostats, diffusers)
  • Automation and AV system programmed and commissioned

What to Do

Interior finishes are the most schedule-sensitive and quality-visible phase of construction. This is where the project transitions from an impressive structural shell to a finished luxury home — and where the quality of your design team, GC superintendent, and finish subcontractors becomes fully visible.

Custom millwork typically has the longest lead time of any interior finish item. A well-regarded Miami millwork shop running at capacity requires 16–24 weeks of shop fabrication after approved shop drawings. Shop drawings themselves require 4–6 weeks. If millwork is not ordered during design development, it will be on the critical path through this phase, extending the schedule by months.

Stone installation requires sequencing discipline. Large-format stone floors (24x24 and larger) require adequate structural deflection control to prevent cracking — confirm this with your structural engineer. Stone countertops and shower surrounds are templated after cabinets are installed and before fabrication begins; template-to-fabrication runs 3–5 weeks per trade package.

Common Gotchas

  • Millwork not ordered until permits issued, placing it on the critical path by 4–6 months
  • Stone slabs selected from slab yard that later becomes unavailable — buy complete slab quantity at selection time
  • Automation programming and AV commissioning underestimated — budget 4–8 weeks for a sophisticated system
  • Paint sequence: premium finishes require 2–3 coats with sanding between, taking significantly longer than budget-grade paint schedules

Phase 11: Punchlist, Commissioning, and Certificate of Occupancy

Typical Duration: 4–10 weeks

Key Roles

GC, owner's rep, architect (punch inspection), all trade subcontractors, commissioning engineer (MEP), building official (final inspection).

Deliverables

  • Joint punchlist walkthrough completed
  • Punchlist items corrected and re-inspected
  • MEP systems commissioned and tested
  • Automation/AV systems demonstrated to owner
  • Final building inspection passed
  • Certificate of Occupancy issued
  • As-built drawings delivered
  • Operations and maintenance manuals delivered
  • Manufacturer warranties documented and transferred

What to Do

The punchlist inspection should be conducted jointly by the owner (or owner's rep), the architect, and the GC superintendent. Do not rush this walkthrough — a thorough inspection of a 7,000+ sqft luxury home takes a full day. Bring a detailed checklist organized by room and system. Photograph every punchlist item with location and description.

Mechanical commissioning is a distinct activity from rough-in inspection. All HVAC equipment must be balanced (airflow measured and adjusted), tested against design conditions, and documented. Ask for commissioning reports for every major system — HVAC, plumbing, electrical, generator, pool/spa, irrigation, and home automation.

The building official's final inspection is the gate to the Certificate of Occupancy (CO). In Miami-Dade, the CO process requires sign-offs from all reviewing trades (building, electrical, mechanical, plumbing, zoning) and may involve multiple inspectors. Allow 1–3 weeks from final inspection submission to CO issuance.

Common Gotchas

  • Punchlist items that require re-ordering materials (hardware, fixtures) extending completion by weeks
  • Final inspection comments requiring additional work before sign-off
  • As-built drawings not maintained during construction, requiring reconstruction from field conditions
  • Generator and propane system inspection requiring separate fire marshal sign-off

Phase 12: Move-In, Documentation, and Warranty Period

Typical Duration: 12 months active warranty

Key Roles

Owner, owner's rep (warranty management), GC, all subcontractors, furniture and decor vendors.

Deliverables

  • Move-in coordination complete
  • Systems orientation: owner trained on all home systems
  • 90-day warranty inspection and punch-out
  • 11-month warranty inspection and punch-out
  • All warranty claims documented, submitted, and resolved

What to Do

Conduct a formal 90-day post-occupancy inspection to identify defects that only appear under live conditions (HVAC performance in various weather conditions, plumbing leaks under use, automation programming issues, settlement cracks). A second inspection at 11 months captures items before the standard 1-year contractor warranty expires.

Document all warranty claims formally in writing to the GC. Under Florida law, Chapter 558 of the Florida Statutes governs construction defect claims — following the proper notice procedure is essential for preserving your rights. Your owner's rep or construction attorney can guide this process.

The move-in period is also when the FF&E (furniture, fixtures, and equipment beyond built-ins) is installed. A luxury home's decorating and furnishing program — managed by the interior designer — typically runs 6–12 months after CO and involves coordinating dozens of vendors, import timelines, and installation sequencing. Budget for white-glove moving and installation services for valuable furniture and art.


Total Timeline Summary

Phase Duration Cumulative (from Day 1)
1. Pre-purchase due diligence2–4 wks1–1.5 months
2. Architect selection + schematic8–12 wks3–4.5 months
3. Owner's rep + preconstruction4–6 wks (overlaps)4–5 months
4. Design development + engineering12–16 wks7–9 months
5. Permitting + ARB12–30 wks10–16 months
6. GC selection + GMP6–10 wks (overlaps 5)11–18 months
7. Site prep + demolition4–12 wks12–20 months
8. Foundation + structural shell16–26 wks16–26 months
9. MEP rough-in + dry-in12–20 wks (overlaps 8)20–30 months
10. Interior finishes + cabinetry18–32 wks25–38 months
11. Punchlist + CO4–10 wks26–40 months
12. Move-in + warranty12 months ongoing38–52 months total

The above represents the outer envelope including parallel activities. A well-run luxury custom home — with an engaged owner, experienced architect, proactive permit expeditor, and skilled GC — typically achieves CO in 20–26 months from Phase 1 start. Poorly managed projects or those in highly restricted jurisdictions can take 36–48 months.

Frequently Asked Questions

How long does it take to build a luxury custom home in Miami from start to finish?

The full timeline from contract execution through certificate of occupancy typically runs 18–30 months for a luxury custom home in Miami, with complex estates or projects in restricted jurisdictions reaching 36–48 months. Permitting is the greatest schedule variable: Miami Beach can take 12–18 months for complex permits, while some inland municipalities process in 8–12 weeks. Early engagement with a permit expeditor and a well-organized architect significantly compresses the schedule.

Do I need to own the lot before starting the design process?

No, but you should have the lot under contract before investing significantly in design fees. Pre-purchase due diligence (Phase 1 in this guide) will identify zoning constraints, setback requirements, lot coverage limits, and any deed restrictions that define what can be built. It is common and advisable to commission a feasibility study and preliminary massing concept during the due-diligence period before closing on the land.

When do I need to hire an owner's representative?

Ideally before you select an architect. An experienced owner's representative helps scope the architect selection, establishes the project program, sets realistic budgets, and manages the design team on your behalf. On projects above $3–5 million, the fee for a qualified owner's rep (typically 3–5% of hard construction cost) consistently delivers positive ROI through better design management, competitive procurement, and disciplined change-order management during construction.

What is a GMP contract and why does it matter?

A Guaranteed Maximum Price (GMP) contract caps the owner's exposure to cost overruns above a negotiated ceiling. Savings below the GMP may be shared between the owner and GC depending on the contract structure. A GMP requires sufficient design completion (typically 60–90%) to be meaningful — a GMP signed against schematic-level drawings provides little real protection. Insist on a GMP only after design development or construction document completion.

What happens if I want to make changes after construction starts?

Changes after construction starts generate "change orders" — formal amendments to the construction contract. On luxury projects, change orders routinely add 8–20% to original contract value, even with disciplined owners. Miami's specialty subcontractors charge significant premiums for out-of-sequence work. The discipline of freezing design before construction begins — and completing interior selections during design development, not mid-construction — is the most reliable way to control change-order exposure.

How do I find and vet a luxury home architect in Miami?

Review published projects in similar neighborhoods, visit completed homes if the architect can arrange it, check that the architect holds a current Florida license (verify at DBPR), and confirm they have specific experience with Miami-Dade Building Department submittals and HVHZ structural detailing. Interview at least three firms. Understand the fee structure: full-service architecture typically runs 8–14% of construction cost for custom luxury homes.

What is threshold inspection and do I need it?

Florida Statute 553.79 requires threshold inspections for buildings that exceed certain size, height, or structural thresholds. For a typical large luxury single-family home in Miami, threshold inspection may be required depending on the structural system. Your structural engineer and building official will advise. Threshold inspectors are licensed engineers who observe and record critical structural elements during construction — they provide an independent quality assurance layer above routine municipal inspections.

What does the punchlist phase involve?

The punchlist is a formal list of incomplete or defective work items identified during a joint owner/GC walkthrough near completion. On a luxury project, a thorough punchlist typically has 200–600 items, ranging from paint touch-ups to incomplete hardware installation to commissioning of mechanical systems. The punchlist phase takes 4–10 weeks to complete. Retain 5–10% of the contract amount as retainage until punchlist completion and final certificate of occupancy are received.

What warranty comes with a new custom home in Miami?

Florida Statute 553.84 provides an implied warranty of fitness for a new home. Additionally, most GC contracts include an express 1-year workmanship warranty and pass through manufacturer warranties on systems (HVAC, roofing, appliances). Some builders offer extended structural warranties. Get all warranty terms in writing before executing the construction contract. Document all systems and commissioning data for warranty claims.

Can construction happen during South Florida hurricane season?

Yes. South Florida's hurricane season (June 1 – November 30) does not halt construction, but it requires active preparedness. GCs must have a hurricane preparedness plan, materials must be secured or removed before named storms, and construction schedules should build in 2–4 weeks of weather contingency for major storm events. June–October in South Florida also brings daily afternoon thunderstorms that reduce exterior work productivity by 15–25% compared to dry-season months.

What is ARB review and does my project need it?

An Architectural Review Board (ARB) or Board of Architects reviews new construction in certain jurisdictions (Coral Gables, Miami Beach Historic Districts, Coconut Grove, some HOAs) to ensure design quality, neighborhood compatibility, and compliance with local design guidelines. ARB review adds 4–12 weeks to the permitting process and may require design revisions. Projects in Coral Gables are reviewed by the Coral Gables Board of Architects, which has among the most detailed design standards in South Florida.

Ready to Build?